Weekly PMO Dashboard

REMAT Municipal Innovation Hub — Project Progress Dashboard

Live weekly reporting view for REMAT leadership · Update inline before each status meeting

REMAT AL-RIYADH
شركة ريـمـات الرياض للتنمية
Project Name
REMAT Municipal Innovation Hub
Reporting Week
Week 7 of 16
Reporting Date
05 July 2026
Current Stage
II. Strategic Positioning
Overall Health
ON TRACK
Prepared By
FTI Consulting
Project Timeline16-week design phase · today marker included
I. Diagnostic & Prep. Analysis
II. Strategic Positioning
III. Concept Design & Delivery Model
IV. Governance & Operating Model
V. Implementation Roadmap
VI. BoD Presentation
Key Meetings
Today · Wk 7
Completed In Progress Not Started | Kick-off Meeting w/ REMAT CEO Meeting w/ HH Meeting w/ BoD
Progress Against Plan
44%
Overall Progress (Actual)
7 / 16
Weeks Elapsed / Total
48%
Planned Progress (Baseline)
Weekly Milestones & Upcoming MeetingsWeek 7 of 16

Completed Milestones

  • Current state assessment of KSA innovation ecosystem finalized
  • Municipal service domains identified and prioritized
  • Benchmarking of leading global innovation hubs completed
  • Gap analysis presented to REMAT CEO

Upcoming Milestones

  • Finalize preferred positioning & value proposition (Week 8)
  • Draft Innovation Hub Strategy document (Week 8-9)
  • Strategy sign-off with REMAT leadership (Week 9)
  • Kick off Concept Design workstream (Week 8)

Key Upcoming Meetings

Project Stage TrackerClick a stage to expand sub-tasks, achievements, next steps & risks
Completed In Progress Not Started
Deliverables TrackerClick a row to expand key update · Dummy data for illustration
Deliverable
Status
Completion
Target Date
Next Steps & Support Required
Next Step / Support Type Responsible Party Due Date Priority Risk if Not Resolved
Confirm budget envelope for Year 1 competitions Decision REMAT Finance 12 Jul 2026 High Delays go-to-market strategy design in Stage III
Provide access to municipal service performance data Data / Access REMAT PMO 10 Jul 2026 High Gap analysis validation delayed for 2 service domains
Nominate stakeholders for positioning workshop follow-up Stakeholder Access REMAT CEO Office 14 Jul 2026 Medium Reduced input diversity on positioning options
Approve Meeting with HH scheduling window Approval REMAT Chairman's Office 16 Jul 2026 High Strategy sign-off milestone (Week 9) at risk of slipping
Share existing brand guidelines for Innovation Hub identity Data REMAT Marketing 18 Jul 2026 Low Minor rework needed later in Stage III materials
Weekly Dashboard · REMAT Innovation Hub